Cruise
dates |
Ship |
Comments |
Cruise
Report /photos |
2000 |
|
Castor-02 |
Deployment of the full mooring line. Qualification deployment without instrumentation (buoy v1) |
|
#2, Oct 19-21 |
Castor-02 |
Recovery of buoy v1. The mooring line remains on site |
|
2002 |
#3,May 15-17 |
Castor-02 |
Deployment of buoy v2 (carbon fiber), plus the full instrumentation suite. |
|
#4, Jun 13-15 |
Castor-02 |
Tentative recovery of some equipment after the buoy had sunk... |
|
2003 |
#5, Sep 5-7 |
Castor-02 |
Deployment of buoy v3 (aluminum and steel), plus the full instrumentation suite |
|
#6, Nov 30 |
Castor-02 |
Unsuccessful attempt to recover the buoy (bad weather) |
|
#7, Dec 5-7 |
Castor-02 |
Recovery of the upper superstructure |
|
2004 |
#8, Feb 13 |
Castor-02 |
Unsuccessful attempt to deploy the buoy (bad weather) |
|
#9, Mar 3-5 |
Castor-02 |
Deployment of buoy upperstructure v3, including the full instrumentation suite |
|
#10, Jul 23 |
GG-IX + helicopter |
Rotation of the upper buoy superstructure |
|
2005 |
#11, Jun 2-4 |
Castor-02 |
Recovery of the full mooring line and buoy |
|
#12, Jun 15-17 |
Castor-02 |
Deployment of a new morring line and a new buoy |
|
2006 |
#13, Jun 9-10 |
GG-IX + helicopter |
Rotation of the upper buoy superstructure |
|
2007 |
#14, Feb 22-23 |
GG-IX + helicopter |
Rotation of the upper buoy superstructure |
|
#15, Sep 20-23 |
Castor-02 + helicopter |
Exchange of the full mooring line + buoy |
|
2008 |
#16, Jan 20 |
GG-IX + helicopter (HDF) |
Upper superstructure recovery |
|
#17, 13 Mar |
Tethys-II |
Lower superstructure and mooring line recovery |
|
#18, 20 Jun |
Castor-02 |
Deployment of the mooring line and the lower buoy superstructure |
|
#19, 28 Jun |
GG-IX + helicopter (HDF) |
Deployment of the buoy upper superstructure |
|
2009 |
#20, Apr 5 |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
#21, Oct 27 |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
2010 |
#22, Apr 22 |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
#23, Sep 1-3 |
Castor-02 |
Recovery of the buoy upper part, plus rotation of the full mooring line |
|
#24, Sep 4 |
Castor-02 + helicopter |
Deployment of the upper buoy part |
|
2011 |
#25, Apr 1 |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
#26, Sep 16 |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
2012 |
#27, 7 Sep |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
2013 |
#28, Jun 13-14 |
Castor-02 + helicopter |
Rotation of the entire buoy and mooring line |
|
2014 |
#29, Mar 14 |
GG-IX + helicopter (HDF) |
Rotation of the upper buoy superstructure |
|
2015 |
#30, May 10-11 |
GG-IX |
Rotation of the upper buoy superstructure |
|
2016 |
#31, Jun 6-7 |
GG-IX |
Rotation of the upper buoy superstructure |
|
#32, Aug 26-29 |
CASTOR 02 |
Rotation of the lower buoy superstructure and mooring line |
|
2017 |
#33, Jun 1-2 |
GG-IX |
Rotation of the upper buoy superstructure |
|
2018 |
2019 |
#34, Feb 15-16 |
GG-IX |
Rotation of the upper buoy superstructure |
|
#35, Sep 15-18 |
Castor-02 |
Deployment of the mooring line |
|
2020 |
#36, Aug 10-11 |
GG-IX |
Rotation of the upper buoy superstructure |
|
2021 |
2022 |
#37, Jun 30-Jul 1 |
GG-IX |
Rotation of the upper buoy superstructure |
|
2023 |
#38, Jul 11 |
Ideal IV |
Recovery of the upper buoy superstructure |
|